The LAX People Mover project is facing a new lawsuit. Here’s the latest

πŸ“Ί LAist πŸ• July 14, 2026 at 5:02 PM
Three cars of a white train and black windows are visible on a gray track. There is a white arch behind the train. In the furthest background, there is a tower.
The project, a 2.25-mile-long elevated train designed to transport riders between airport terminals and local transit, is currently undergoing testing.(Kavish Harjai / LAist)

The contractor building the long-awaited LAX People Mover project has filed a lawsuit alleging the city of L.A. breached its contract in several disputes.

In the suit, filed with the L.A. County Superior Court on July 9, LINXS alleges the city is misplacing blame in construction-related disputes and refusing to extend contract deadlines. LINXS also alleges it’s owed additional payment for the work as a result of the delays.

The project, a 2.25-mile-long elevated train designed to transport riders between airport terminals and local transit, is currently undergoing testing. Work on the train is scheduled to be complete β€œin a few months,” according to a June interview with Los Angeles World Airports CEO John Ackerman on the L.A. in a Minute podcast.

Chief among the disputes detailed in the lawsuit is one involving repairs to faulty electrical equipment in the system that powers the train, resulting in testing delays last year. LAist reported on this dispute last November and in April.

A spokesperson for LINXS said it has attempted to engage in β€œextensive good-faith efforts over the past two years” to resolve the ongoing contractual disputes.

A spokesperson for Los Angeles World Airports, the city agency that manages LAX, said the agency does not comment on pending litigation. They added that the agency remains committed to β€œdelivering a safe, durable and reliable” train as soon as possible.

The L.A. City Attorney’s office did not immediately respond to requests for comment.

In its lawsuit, LINXS said that by not granting the contractor’s compensation and time-extension requests, the city is attempting to evade accountability for the delayed train, which was once expected to open in 2023 and is nearly a billion dollars over budget.

The contractor warned in its lawsuit that without an extension of contract deadlines, it might be forced to repay lenders who financed the project as soon as this fall. In that case, the contractor said in its lawsuit that it could become β€œinsolvent and unable to perform,” adding that possibility would have β€œcatastrophic consequences.”

Dispute over metering cabinet

Last February, staff from Los Angeles World Airports and the city’s Department of Water and Power directed LINXS to repair equipment in a metering cabinet that had degraded due to moisture and debris, as LAist previously reported.

LINXS completed the repair work, which required power to be partially shut down between February and July 2025. That temporary power disruption delayed critical testing of the technology that allows for central control of the People Mover’s systems.

LINXS said last year, and also in the current lawsuit, that the repair work is not in its scope of work. As a result, the contractor has said it’s owed compensation and a minimum of a 141-day extension to complete construction.

β€œSince then, [Los Angeles World Airports] has stonewalled the discussions of [LINXS’] compensation and a time extension,” the contractor alleges in its lawsuit.

LINXS, citing information it received from a public records request, alleges the issue stemmed from an instance where LADWP opened the metering cabinet in September 2024 to rectify design issues with the equipment contained in it.

Whereas past disputes between LINXS and the airport were resolved through settlements that have so far totaled hundreds of millions of dollars and resulted in schedule extensions, the dispute over maintaining electrical equipment has been uniquely contentious.

β€œOther relief events that we’ve dealt with up to this point … we could agree there were some things that were not totally within LINXS’ control,” Jake Adams, an airport executive who is overseeing $5.5 billion in LAX upgrades, said in an interview with LAist in April. β€œThis relief event is very different. We believe there is absolutely no merit to this claim.”

The lawsuit also alleges that the contractor is owed additional time and money for several other ongoing disputes, including that Los Angeles World Airports is refusing to sign a power agreement with LADWP for solar panels installed as part of the People Mover project and that workers on separate airport projects have β€œdemolished” work LINXS completed for the train.

What’s the status of the People Mover?

The People Mover is operating in a testing phase where it simulates how the train will operate when it begins shuttling travelers between airport terminals and the L.A. Metro system.

The testing of the train won’t be impacted by the lawsuit, a spokesperson for Los Angeles World Airports told LAist.

A hearing on the case filed last week has been scheduled for December, according to the L.A. County Superior Court’s website.